Project Update 12
The Trustee advises: · With wet weather and public holidays, there were only 17 work days on site in April. · Work was delayed as the contractor encountered unsuitable fill material, which had to be excavated and removed off-site; these works are continuing. · Bulk earthworks are nearing completion, with the transport of fill on […]