Sara Summers

The Trustee advises: · With wet weather and public holidays, there were only 17 work days on site in April. · Work was delayed as the contractor encountered unsuitable fill material, which had to be excavated and removed off-site; these works are continuing. · Bulk earthworks are nearing completion, with the transport of fill on […]

The Trustee is pleased to announce that civil works has commenced of site at 139 Bunya Road, Arana Hills. • The remaining tenant has vacated• The body corporate of adjoining property and neighbours notified of impending work via Surveyor• The asbestos contractor has completed asbestos removal from the house onsite, ready for demolition contractor• The […]

The Trustee is pleased to announce that the Moreton Bay Regional Council has approved Development Application No.: DA/2024/1736, at Lot 1 B 3346, 139 Bunya Road, Arana Hills. The approval allows for the subdivision of Lot 1 into two lots. This subdivision is consistent with the Trustee’s previous announcements, Project update 9 and Project update […]